July 7, 2023 | High Reservoir Liner Installed

The installation of the liner for the high reservoir has been successfully completed, marking a significant milestone. Furthermore, the installation of the floating cover has commenced this week, bringing us closer to the project's completion.

In the upcoming phases, our focus will be on commissioning the new piping network, a crucial step in ensuring the seamless functionality of the reservoir.

As a reminder, please note that irrigation restrictions will remain in effect until the high reservoir is fully operational again. We appreciate your understanding and cooperation during this period. 

Irrigation restrictions will remain in effect until the high reservoir is back online. 


Show All Answers

1. January 18, 2023 | Rupture Occurred
2. January 19, 2023 | Council Approves Resolution for Emergency Spending
3. January 25, 2023 | Reservoir Drained and Isolated from System
4. January 26, 2023 | Boil Water Order Lifted
5. January 23, 2023 | Council Issues a Continuance of Local Disaster Emergency
6. February 7, 2023 | Mayor Issues Order Terminating Local Disaster Emergency
7. February 23, 2023 | Technical Update Provided to Staff
8. March 27, 2023 | Council Approved Recommendation to Reuse the High Reservoir
9. April 17, 2023 | Discovery that First Plan was No Longer Viable
10. May 2, 2023 | Irrigation Restrictions Begin for Affected Water Customers
11. May 3, 2023 | Council Amends Emergency Expenditures Resolution
12. May 4, 2023 | Council Approves Second Proposed Plan and Contractor Moves Forward
13. May 12, 2023 | Demolition Begins
14. May 19, 2023 | Demolition is Complete
15. June 5, 2023 | Working with the DEQ
16. June 20, 2023 | Restoration Project is 65% Complete
17. July 7, 2023 | High Reservoir Liner Installed
18. July 31, 2023 | Irrigation Restrictions Lifted